Standard AIA 5-Phase Fee Allocation (15 / 20 / 40 / 5 / 20)
While every architecture firm negotiates exact percentages in Article 11 of AIA B101, the classical residential and commercial Basic Services split allocates 15% to Schematic Design (SD), 20% to Design Development (DD), 40% to Construction Documents (CD), 5% to Bidding or Negotiation, and 20% to Construction Administration (CA).
Because Construction Documents absorb 40% of total architectural effort (dimensioned plans, sections, wall assemblies, window/door schedules, and consultant coordination for permit submittal), switching structural schemes or floorplan footprints after DD sign-off is the single largest driver of Additional Services fees.
| Phase Code | AIA Basic Service Phase | Typical Share | Primary Deliverables & Milestone Gate |
|---|---|---|---|
| SD | Schematic Design | 15% | As-built review, zoning/setback diagram, 2–3 floorplan options, preliminary massing & order-of-magnitude budget range |
| DD | Design Development | 20% | Locked floorplans, exterior elevations, structural grid coordination, window/door sizing, MEP & Title 24 / IECC coordination |
| CD | Construction Documents | 40% | Permit-ready technical drawing set, wall sections, construction details, schedules, municipal plan-check response cycle |
| BN | Bidding & Negotiation | 5% | Issuing bid sets to vetted general contractors, answering pre-bid RFIs, bid leveling spreadsheets & value engineering |
| CA | Construction Administration | 20% | Periodic site observation visits, reviewing contractor submittals/shop drawings, RFI responses, pay-app certification & punch list |
Fee Models: Percentage of Construction Cost vs. Fixed Fee vs. Hourly
Percentage-of-construction-cost fees commonly range from 8% to 12% for straightforward ground-up custom residences and 10% to 15% (occasionally higher) for complex kitchen/whole-home remodels and hillside ADUs where existing structural conditions consume extra investigation hours relative to construction volume.
Fixed-fee contracts convert that percentage into a locked dollar figure based on a clearly bounded scope and gross square footage — often paired with hourly Additional Services rates ($150–$325/hr depending on principal vs. project architect role and metro market) if the owner expands the program mid-design.
Crucially, engineering consultants (structural engineer, geotechnical soils report, licensed boundary/topographic land surveyor, MEP/Title 24 energy consultant) and municipal plan-check/impact fees are usually contracted separately or billed as reimbursable sub-consultants outside the base architectural percentage.
Worked Example: 750 sq ft Detached ADU at $425/sq ft
Hard construction cost = 750 sq ft × $425/sq ft = $318,750. At an 11% Basic Services architectural fee ($35,063), the phase billing milestones break down cleanly as: Schematic Design $5,259 (15%), Design Development $7,013 (20%), Construction Documents $14,025 (40%), Bidding $1,753 (5%), and Construction Administration $7,013 (20%).
Adding structural/MEP engineering (~3.5% = $11,156) and municipal permit/plan-check fees (~4.0% = $12,750) brings total soft costs to $58,969 (18.5% of hard cost) and total all-in project budget to $377,719 before owner contingency.